Alleged narco trafficker makes first US court appearance
-
Neymar misses out as Endrick returns to Brazil squad
-
South Lebanon's Christian towns insist they are not part of Israel-Hezbollah war
-
Alleged narco trafficker Marset makes first US court appearance
-
Securing the Strait of Hormuz: Tactics and threats
-
Cuba hit by total blackout as US fuel blockade bites
-
'Buffy' reboot cancelled: Sarah Michelle Gellar
-
Damaged Russian tanker has 700 tonnes of fuel on board: Moscow
-
PSG will go for the kill against Chelsea: Dembele
-
Afghan govt accuses Pakistan after new strikes on Kabul
-
Chelsea huddle not meant to 'antagonise' says Rosenior
-
Talks towards international panel to tackle 'inequality emergency' begin at UN
-
Trump pushes for 'enthusiasm' from allies to secure Hormuz
-
US, China hold 'constructive' talks on trade, but Trump visit in doubt
-
Laporta's new Barca chapter begins with Newcastle clash
-
EU talks energy as oil price soars
-
Out-of-favour Livingstone says 'no-one cares' in England set-up
-
Rising star Antonelli says Chinese GP triumph 'starting point' for F1 success
-
Stagflation risk in US 'quite high': Nobel-winning economist Stiglitz
-
Swiss government rejects proposal to limit immigration
-
Ingredients of life discovered in Ryugu asteroid samples
-
Why Iranian drones are hard to stop
-
Teen star Dowman ready to make impact for Arsenal says Arteta
-
Jones says England would be 'foolhardy' to sack Borthwick before Rugby World Cup
-
Man City must be 'perfect' to stun Real Madrid: Guardiola
-
Ntamack set for Toulouse return at Bordeaux-Begles
-
Hours-long fuel queues in Laos capital Vientiane
-
France threatens to block funds for India over climate inaction
-
Will Yemen's Houthis join the Mideast war?
-
Oscar winner Sean Penn skips ceremony to visit Kyiv
-
Rise of drone warfare sharpens focus on laser defense
-
Nepal welcomes first transgender lawmaker
-
Rooney says patience needed with Premier League record-breaker Dowman
-
Spain court rejects trial for ex-govt leader over deadly 2024 floods
-
"So proud": Irish hometown hails Oscar winner Jessie Buckley
-
'Hollywood story': Russia's Mr Nobody makes history with Oscar win
-
City boss Guardiola still has hope of revival against Real Madrid
-
Iran, at UN, insists will not submit to 'lawless aggression'
-
Appeal trial opens for France's Sarkozy over alleged Libyan funding
-
Szoboszlai warns time against Liverpool in quest for Champions League place
-
Israel army says begun 'limited targeted ground operations' against Hezbollah in south Lebanon
-
Western allies push back on Trump call for NATO help to reopen Hormuz
-
Central banks meet as Mideast war fuels inflation fears
-
European bank battle heats up as UniCredit swoops for Commerzbank
-
Oil eases on hopes for Strait of Hormuz passage
-
Race for Paris mayor on knife's edge after first round
-
Denmark's election candidates bare all in sauna campaigning
-
Russia targets Kyiv at rush hour, kills 3 across Ukraine
-
Iran defiant as strikes hit Gulf transport, energy hubs
-
Frenchman jailed in Azerbaijan for 10 years for 'spying'
Ireland's data centres power digital age, drain the grid
Ireland hosts one of the world's fast-growing clusters of data centres, but is running headlong into the difficult consequences.
The server farms powering global tech giants now consume a fifth of the small nation's electricity, igniting concerns over both grid stability and Ireland's commitments to boost renewable energies and cut gas emissions.
Already home to over 80 data centres, a 2024 report by US-based researchers Synergy ranked Dublin behind only the US state of Virginia and Beijing in its density of such state-of-the-art facilities built for colossal amounts of data.
Vast energy-hungry warehouses around Dublin's ring road host thousands of servers handling massive amounts of cloud computing, storage and AI demands for data giants like Google, Meta, Microsoft and Amazon.
The facilities are a quietly purring economic engine, injecting billions in investment, employment and anchoring the tech multinationals which, coupled with big pharma, fund over half of Ireland's corporate-tax take, according to analysts.
But doubts are mounting over the environmental cost.
- 'Unsustainable' -
Campaigner group Friends of the Earth told AFP such centres are "completely unsustainable".
"It's one of the fundamental climate justice issues of our times," said spokesperson Rosi Leonard.
Data centres' share of Irish metered electricity consumption reached 22 percent by 2024, compared to an EU-wide average of 2-3 percent, according to official data.
National grid operator EirGrid projects that data centres could account for 30 percent of demand by 2030 as the growth of artificial intelligence technology accelerates.
That is equivalent to powering two million homes for a full year, energy analysts Wood Mackenzie said in July.
Some data centres in high-pressure areas in Dublin have already turned to generators for back-up, which are usually gas and oil-powered, said Leonard.
That could hamper Ireland's already fraught efforts to meet EU 2030 climate targets that threaten multi-billion euro fines if missed.
Leonard said the server farms are also gobbling up much of the renewable energy like wind and solar that is being added to the grid.
"We want a moratorium on further expansion of data centres until they pose no threat to our climate and carbon budgets," she said.
- 'Limbo' -
EirGrid plans capacity upgrades to accommodate future data centre demand more evenly nationwide. And the government has said a new strategy will be published soon with a pledge to update the grid within five years.
But experts doubt whether those plans will deliver in time to meet demand.
As Ireland aims "to reduce emissions... expanding a sector that's going to increase emissions very significantly just... doesn't make sense," said Barry McMullin, a climate change expert at Dublin City University.
Data centre compatibility with emissions goals "is unlikely for another decade", he told AFP.
Some planning authorities have already pushed back.
Last year, a local council in Dublin refused a Google data centre development, citing "insufficient (grid) capacity" and a "lack of significant on-site renewable energy".
Ireland's digital sector contributes an estimated 13 percent to GDP.
But Maurice Mortell, head of Digital Infrastructure Ireland (DII), a group representing data centres, warns the nation could lose out on AI-driven investment due to grid and planning blockages.
"We've over 18 billion euros ($21 billion) of investment in digital infrastructure here already, with another 5.8 billion planned, but without power, so potentially marooned," he said.
"Ireland's lead, particularly in cloud computing, is at risk," he told AFP, highlighting its fading appeal and frustrations from large US firms.
"Our sector is in limbo, we need a grid that's capable, and a clear policy environment," he said.
- Waste heat -
A 2022 government strategy paper said data centres should demonstrate a "clear pathway to decarbonise" and "net-zero data services by design".
Meanwhile, a project launched in 2023 by Amazon Web Services (AWS) in partnership with a local Dublin authority shows how some climate impacts could be offset.
Waste heat provided from an AWS data centre is carried via hot water through pipes to a local heating hub next door to heat offices and a library, and soon hundreds of homes.
"There is potential for other data centres to do the same," said Admir Shala, a project manager at the heating hub called Heatworks.
But expert McMullin was sceptical.
"We don't really have heat networks to plug this waste heat into," he said, adding that data centres run year-round whereas homes only need to be heated for about six months a year.
R.Chavez--AT